How Does Buying a New Industrial Unit at Penjuru Connection Work?

Buying a unit at Penjuru Connection follows the usual pattern for a new industrial development: an option to purchase, an eight-week period in which 20% of the price is paid and the Sale and Purchase Agreement is signed, then staged payments as construction progresses. The building has not yet been put up, so most of the price is paid over the construction years rather than at the start.

Step One at Penjuru Connection: Registering and Choosing a Unit

Before anything is signed, the developer has to release its sales material: the price list, the floor plans and the e-brochure. For Penjuru Connection these particulars, including the unit sizes, the number of storeys and the specifications, will be published by the developer in due course. Registered buyers receive each one as it is issued, which is the simplest way to be ready when units are offered.

Once you have shortlisted a unit, check the use you intend against the B2 zoning. The project details page sets out the confirmed facts, and the industrial loan page explains why many lenders prefer a company as the borrower for a B2 purchase, which is worth settling early.

The First Eight Weeks of a Penjuru Connection Purchase

The first part of the purchase runs to a tight timetable of roughly two, three and three weeks. It begins when the developer grants an option to purchase and ends with 20% of the price paid.

WhenWhat happensPayment
Option grantedOption fee paid by cheque or cashier's order5% of the price plus GST
About two weeks laterThe Sale and Purchase Agreement arrives; have the bank's letter of offer signed before meeting the law firmNone
Within three weeks of receiving itThe S&P is exercised; Buyer's Stamp Duty is paid to IRAS, with the legal feeBSD and legal costs
About three weeks after thatBalance of the down payment15% of the price plus GST

Indicative timeline for a new industrial development under construction. Exact terms are set out in the option and the S&P.

Two points catch out buyers who are used to homes. GST is added to each payment, including the option fee, and the S&P must be exercised within three weeks of receipt, so the financing and the buying entity need to be settled before the option is taken. The stamp duty and GST page covers the duties payable during this window.

Construction-Stage Payments at Penjuru Connection

After the first 20%, the rest of the price is paid as the building reaches each milestone. Industrial developments use their own schedule of stages and percentages.

StageShare of the price
S&P period (option and balance down payment)20%
Foundation work completed10%
Reinforced concrete framework completed10%
Walls completed5%
Ceiling completed5%
Doors and windows completed5%
Electrical, sanitary and air-conditioning works completed5%
Car park, roads and drains completed5%
Temporary Occupation Permit (TOP)25%
On completion10%

Standard progressive payment schedule for industrial and commercial property under construction. GST at 9% is charged on each instalment.

Each stage instalment is normally drawn from the bank loan once the down payment has been made, while the GST on it is paid in cash. The payment scheme page explains every stage, and the purchase calculator shows the cash and loan split for any price you enter.

How Long the Penjuru Connection Build Is Expected to Take

The developer has not yet announced an expected TOP date for Penjuru Connection. What is known is the framework set by JTC: the tender conditions for the Penjuru Road land parcel, awarded on 23 January 2026, include a project completion period of 84 months. That is the outer limit within which the development is to be completed, not a forecast of when it will be ready.

In practice, the construction-stage instalments are spread across the building period, with the largest single payment, 25%, falling due at TOP and the final 10% on completion. Planning the cash flow therefore means planning for several years of staged payments rather than one lump sum.

Preparing for the Penjuru Connection Release

It also helps to know who will sign. Where the buyer is a company, the board resolution, the authorised signatories and the company stamp, if used, should be ready, because the option and the S&P are company documents and the bank will want them in order before it releases the loan.

Buyers who move smoothly through the eight-week window tend to have three things in place beforehand: the buying entity, an in-principle loan approval, and a law firm briefed on industrial conveyancing. With those settled, the decision when the price list arrives is about the unit, not the paperwork.

Showflat viewings are arranged by appointment through the Sales Concierge. Each of the price list, the floor plans and the e-brochure goes by email to firms on the Penjuru Connection register the day it appears.